Thanks for clarifying that. Don't mind Jomoco, while he is very experienced and knowledgable, he's not known for understating things, or running away from an argument.....
I'm considering passing on bidding on a massive black cottonwood, as I think it would be hard to do it in a day. Involves parking a 100 ton crane in the street, with only room for cars, not buses to pass, without sucking in the outriggers (That's a pain.) If done Dec 27-28 (no school buses), We could do it without double or 1.5 time for crane and flaggers. But I'd still bid close to $15,000!!
Another co thinks they can do it in a day. Assume 10 hours of crane time with 1 hr travel each way. Can a crane that carries it's own c/w's set up on a nearly level road in 30 minutes? Seems a bit fast. That would still be 3 hours out of 10 with no work being done. The tree is at least 65" dbh, 150 feet tall. Not a lot of room to lay down brush or wood. At least 20 picks.....Radius at least 70 feet. With full counterweights, the chart looks adequate. But I'd like to be able to pick 20 foot trunk wood, in order to sell those 3 logs to offset trucking costs.... They'd weigh 7000-10000 lb each.
Do you know the model ?
100 ton with the stone on board, not many out there
they may have a dolly..where the boom is rest for travel..it can also carry the CW..no big deal ..as soon as the boom is out of the dolly ..boom up and hook onto a stone ..bring it on board....normally i would set my mats get on full outrigger's and then bring the CW on board ...all depends on the site really ..
worst case 10,000 pound at 70 feet.
the examples i give are based solely on a 70ft radius.
Grove/GMK-4085_100T best chart 96ft main @ 15,600 /sections 2/3 extended
Demag/AC-80-1_100T best chart 103.2 main @ 15,400/ sections 20/20/74/74/74 ..(those are precentages of main boom extended).
Grove/GMK-4100B_100T best chart 148 main @ 14,000 / sections probably 3/4/5... dosent show it ..
Liebherr/LTM-1090/2_110T best chart 87ft main ..but i think thats short ..so 111 of main @ 18,700lbs ..92/92/46/46/0 ..theres three different boom configs for the 111 fot lenght ..so to speed it up Id just use 0/0/92/92/92..again percentages of main boom sections..
30 minutes is good .... I can set an 80 up from the time i hit the button to deploy the jacks to the time its in the air full main ..under 30..thats if i dont have to set the mats ..just put dunnage there ..and load the CW on ..